1 off combustion air supply fan and distribution system
High capacity secondary combustion chamber 2.0 @ >1050oC
1 off diesel-fired afterburner C temperature controlled
Control panel C automatic operation
Temperature indication primary and secondary chambers 0-1200oC
A secondary afterburning emission control chamber.
A discharge chimney.
Control  panel-  time  and  temperature  dedicated  control  system,  housed  within  an incinerator mounted control 
cabinet
Unit to be capable of burning high calorific value solid, liquid and sludge waste and shall be as modified version of the 
Surefire incinerator by Matthews environmental solutions  or as approved
Supply and install and or fabricate as wet scrubber Model – SF50/1 wet scrubber to be positioned horizontally on the 
chimney and manufactured from mild steel horizontal section painted with enamel paint finish, refractory lined inner 
section with cold face insulation of calcium silicate all to achieve a thickness of 100mm and provide internal diameter 
of 420mm, stainless steel spray nozzle along the refractory lining, stainless steel tank of holding capacity 250litres 
complete with stainless steel float valve, Hot water pump model Daylif DB 2/30 for circulation of hot water in the 
scrubber and galvanised piping complete with valves, strainers and water flow bypass.

Automatically controlled burn and cool down period.
This chamber should be equipped with burners that use low sulphur fuel.
1 Diesel fired Ignition Burner
1 set combustion air distribution pipe work 1 Observation port with protective glass and 1 thermocouple
1 Flue gas outlet to secondary combustion chamber- Should be lined with calcium silicate insulation and a hot face 
combination of super duty brickwork or high strength castable.
Health Care Waste management (HCWM) and would need to implement a semi industrial incinerator 
Feed chamber/charging door.
Control panel C automatic operation
Temperature indication primary and secondary chambers 0-1200oC
Horizontal solid hearth, refractory lined primary combustion chamber 850mm diameter x 2000mm long
Full sized bulk load/ash removal door
2 off diesel-fired ignition burner C temperature controlled
-Perforated  and  filter  panels  for  fly  ash  and  smoke  removal
-Electrical control panel with visual display of temperatures and plant cycles
-Electrically  operated   rising   loading   door   for   hand   charging
-Ash  door  diameter  1460mm,loading  door  670mm  x  600mm
-Other        necessary        accessories        and        testing        fuel
-Installation and overhead costs included